Skip to main content Skip to search Skip to search results

Box 60

 Container

Contains 47 Collections and/or Records:

Procedures to be used during 'D' transposition and docking, September 24, 1968

 Item — Box: 60, Folder: 3, Item: 3
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 22
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: September 24, 1968

Proposed Maneuver for jettisoning the LM descent stage for aborts initiated at TPI° by the LM during the LM active rendezvous (Apollo 9), February 10, 1969

 Item — Box: 60, Folder: 3, Item: 4
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 23
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: February 10, 1969

Propulsion system to be used on the ‘D’ Mission Rendezvous CSI Maneuver, August 5, 1968

 Item — Box: 60, Folder: 3, Item: 5
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 24
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: August 5, 1968

Stable Orbit Rescue for Mission D, November 19, 1968

 Item — Box: 60, Folder: 3, Item: 6
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 25
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: November 19, 1968

Apollo VIII Food System, undated

 Item — Box: 60, Folder: 4, Item: 1
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 26
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: undated

Apollo 8 slidewire status, December 10, 1968

 Item — Box: 60, Folder: 4, Item: 2
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 27
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: December 10, 1968

CSM 103 Ground Test Constraints Plan, October 1968

 Item — Box: 60, Folder: 4, Item: 3
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 28
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: October 1968

CSM 103 Notes (#1)

 Item — Box: 60, Folder: 4, Item: 4
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 29
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: 1968 - 1969

CSM 103 Notes (#2), December 14, 1968

 Item — Box: 60, Folder: 4, Item: 5
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 30
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: December 14, 1968

CM 103, Revision D, Stowage List Change Notice (SLCN), SLCN No. 1D, November 18, 1968

 Item — Box: 60, Folder: 4, Item: 6
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 31
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: November 18, 1968

CSM 103 Status, November 4, 1968

 Item — Box: 60, Folder: 4, Item: 7
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 32
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: November 4, 1968

CSM 103 Status, November 26, 1968

 Item — Box: 60, Folder: 4, Item: 8
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 33
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: November 26, 1968

Crew Debriefing of Crew Compartment Fit and Function, Manned Suit Loop Check-Out S/C 103, July 20, 1968

 Item — Box: 60, Folder: 4, Item: 9
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 34
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: July 20, 1968

Flight Readiness Review for Spacecraft 103 (Command and Service Module 103, Spacecraft Lunar Adapter 11, and Spacecraft Lunar Test Article B), October 15, 1968

 Item — Box: 60, Folder: 4, Item: 10
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 35
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: October 15, 1968

Following Spacecraft hardware will be installed after TCP 0034 testing is completed, undated

 Item — Box: 60, Folder: 4, Item: 11
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 36
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: undated

Minutes of Meeting the Customer Acceptance Readiness Review Phase III Board, CSM 103, at North American Rockwell Corporation, Downey, California, July 25, 1968

 Item — Box: 60, Folder: 4, Item: 12
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 37
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: July 25, 1968

Minutes of the Meeting, The Customer Acceptance Readiness Review Top Deck Buildup Board, CSM 103, at North American Rockwell Corporation, Downey, California, August 9, 1968

 Item — Box: 60, Folder: 4, Item: 13
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 38
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: August 9, 1968

Minutes of Meeting Flight Readiness Review Pre-Board, CSM 103, November 11, 1968

 Item — Box: 60, Folder: 4, Item: 14
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 39
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: November 11, 1968

Spacecraft 103 Configuration Changes and Problems, undated

 Item — Box: 60, Folder: 4, Item: 15
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 40
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: undated

Status of Crew Comments from Simulated Altitude Test and altitude for CM 103, October 22, 1968

 Item — Box: 60, Folder: 4, Item: 16
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 41
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: October 22, 1968

Stowage for TCP K-0007 S/C 103, November 22, 1968

 Item — Box: 60, Folder: 4, Item: 17
Identifier: MSA 5, Series 1, Sub-Series 5, Sub-Group 4, File 8, Item 42
Scope and Contents From the Sub-Group: The Mission Planning files contain those materials essential to the planning and execution of the Apollo program mission, especially the Apollo 11 lunar landing mission. The bulk of the sub-group is retained in Armstrong's original order. However, a significant amount of mission planning material was found throughout the Armstrong papers.
Dates: November 22, 1968

Neil A. Armstrong papers

 Collection — Multiple Containers
Identifier: MSA 5
Scope and Contents The Neil A. Armstrong papers document the military, aeronautics, astronautics, teaching and corporate business career of Neil A. Armstrong. The papers also feature items from Armstrong's youth and education. The collection includes but is not limited to documents, coursework, working papers, subject files, correspondence, writings, speeches, recordings, photographs and newspaper clippings. The papers are divided into eighteen series, and further information on the scope and content of the...
Dates: 1671 - 2012; Majority of material found within 1960 - 2012